Relocation of Sha Tin Sewage Treatment Works to Caverns










 

The funding application for Stage 1 works was approved by Legislative Council Finance Committee Meeting on 26 October 2018 and the works commenced on 28 February 2019. The no. and title of this Contract is DC/2018/05 “Relocation of Sha Tin Sewage Treatment Works to Caverns – Site Preparation and Access Tunnel Construction”. The Contractor is China State Joint Venture. The works of Stage 1 Contract mainly includes:

  • Site Formation;
  • Implementation of natural terrain hazard study mitigation measures;
  • Demolition of existing noise barriers along Ma On Shan road and reprovision of temporary noise barriers;
  • Construction of a steel bridge;
  • Construction of the access road adjoining A Kung Kok Shan Road and the proposed ventilation shaft;
  • Diversion of a section of the existing footpath and cycle track; and
  • Construction of a section of access tunnel

Stage 1 Contract

   
 
 